That four-to-five-year number is the generator queue, and a data center is a load: different process, different rules. ERCOT's Batch Zero load process has been frozen since 3 August with no restart date (thank Governor Abbot's re-election campaign for that), so is the risk a long wait or an open-ended one?

Global Data Center Hub's avatar

Great question. We already have a long wait in most states (4-7 years) and open ended wait period would make a bad situation worse.