Will Digital Edge’s $1B Thailand Bet Outpace Malaysia in the AI Race?
A 100MW campus, $1B in capital, and renewable-backed power: Thailand’s Eastern Economic Corridor stakes its claim as the region’s next AI battleground.
Welcome to Global Data Center Hub. Join investors, operators, and innovators reading to stay ahead of the latest trends in the data center sector in developed and emerging markets globally.
The Groundbreaking That Signals a Shift
When Digital Edge and B.Grimm Power broke ground on their 100MW hyperscale campus in Thailand’s Eastern Economic Corridor (EEC), it wasn’t just another ribbon-cutting ceremony. It was a signal flare: Southeast Asia’s AI infrastructure race is no longer confined to Singapore and Malaysia. Thailand is now in play.
With $1 billion in committed capital, a local renewable energy heavyweight, and a fast-tracked Q4 2026 Ready-for-Service (RFS) target, this project offers a blueprint for how global operators can expand into emerging hubs while balancing speed, sustainability, and scale.
Why This Move Matters
The scale is eye-catching, but the structure is the real innovation.
Powered land, not just land. Digital Edge isn’t speculating on parcels; it’s securing renewable-backed capacity from B.Grimm’s portfolio power that hyperscalers now view as non-negotiable.
Policy-driven incentives. Thailand’s Board of Investment ties tax holidays and regulatory approvals to PUE efficiency and GPU-readiness. That forces projects to be future-proof from day one.
Speed as a moat. June JV announcement, September groundbreaking, Q4 2026 RFS. In a market where power allocation is tightening fast, tempo isn’t marketing spin it’s survival.
Thailand’s Bid to Leapfrog
For years, Singapore dominated the region. Then Johor, Malaysia, became the overflow valve with multi-gigawatt pipelines. But Thailand is no longer a secondary bet:
Data center capacity is projected to triple from 350MW (2024) to 1GW (2027).
AI workloads already account for 28% of demand, up from 20% just a year prior.
$16B+ of inbound commitments in H1 2025 alone, from AWS ($5B), Google ($1B), Microsoft (cloud region), and Bytedance ($8.8B).
This is less “catch-up” and more realignment. The EEC offers abundant land, competitive power costs, and proximity to ports—advantages Singapore can’t replicate at scale.
Competitive Arena: Who Gets There First?
Digital Edge’s 100MW site won’t stand alone for long.
DayOne is building a 120MW Chonburi Tech Park.
Bridge Data Centres is planning a 200MW campus.
Chinese entrants (Galaxy, Haoyang, Stratus) are collectively adding 600MW+ in Rayong.
The race isn’t just about megawatts. It’s about who can convert power + permits into RFS capacity the fastest.
Lessons for Stakeholders
For Operators
Pre-buy long-lead gear. Switchgear and transformers are bottlenecks, not construction crews.
Design for AI heat. Liquid cooling and high-density blocks are table stakes, not future luxuries.
Market sustainability, not just uptime. PUE <1.25 and renewable attributes aren’t side benefits they’re sales hooks.
For Investors
Underwrite partnerships, not just plants. Pairing global operators with local energy incumbents is a proven de-risking play.
Time your entries. Early movers in the EEC get access to the best parcels and feeder lines. Late entrants will pay scarcity premiums.
Watch 2027 bottlenecks. Skilled labor, grid slots, and equipment supply chains will tighten simultaneously.
For Policymakers
Tie incentives to performance. Thailand’s BOI is already forcing GPU/PUE alignment; this keeps the bar high.
Invest in transmission. Without grid resiliency, all the megawatts on paper won’t translate into usable capacity.
The Big Picture
This project is less about one campus in Chonburi and more about a playbook for AI-ready infrastructure in secondary hubs. Pair international execution with local energy incumbents, secure power before demand surges, and move faster than the permitting cycle.
Digital Edge x B.Grimm shows what “operating speed” looks like in an era where AI, not real estate, is dictating the rules of infrastructure.
And the question investors, operators, and policymakers should be asking is: will Thailand’s EEC become the Johor of 2026 or something bigger?