Who Really Wins From Macquarie’s $350M Bet on Fermi America’s 11GW AI Campus?
Inside the risks, politics, and promise of America’s most ambitious AI infrastructure experiment.
Welcome to Global Data Center Hub. Join investors, operators, and innovators reading to stay ahead of the latest trends in the data center sector in developed and emerging markets globally.
The announcement that Macquarie Group is financing Fermi America’s HyperGrid Project a planned 11GW AI-powered campus in Amarillo, Texas is more than a headline about another mega-campus. It’s a test case for whether vertically integrated, behind-the-meter energy models can become the new default in the AI era.
If successful, HyperGrid could rewire how compute is built and powered: bypassing congested grid queues, anchoring AI clusters directly to new nuclear builds, and creating a new class of infrastructure players that are both power companies and data center operators.
But this is also a high-stakes bet. Nuclear timelines, $40B+ in capital needs, and unresolved waste issues make this as risky as it is transformative.
What’s Actually Happening
Financing closed: $100M Series C equity led by Macquarie + $250M senior loan facility (with $100M drawn).
Site: 5,769 acres near Amarillo, Texas, in partnership with Texas Tech University System.
Scale: Up to 11GW of power, 18M sq ft of AI-ready space, enough power for 8–10M homes.
Energy stack: 4× Westinghouse AP1000 reactors, combined-cycle gas, solar + storage, plus grid interconnects for redundancy.
Timeline: First 1GW (gas) online by 2026; first AP1000 reactor by ~2032.
Macquarie’s Joshua Stevens summed it up: Fermi’s “distinctive strategy and ability to tap into near-term power solutions make it well placed to address the fast-growing needs of AI.”
Why This Matters
1. Energy-First Development Is Now Bankable
This is the first major validation from a Tier-1 infrastructure manager that power-first campuses are investable. Hyperscalers have been caught flat-footed by 3–5 year grid delays. Fermi is proving that if you control the power stack, you control the AI growth curve.
2. Texas as AI Power Province
ERCOT demand is already projected to nearly double within five years, driven largely by data centers and AI. Amarillo’s combination of land, political alignment, and community integration (Texas Tech partnership, local EPCs, former Amarillo mayor as community lead) shows how regions are positioning themselves as sovereign compute hubs.
3. Nuclear Re-enters the Data Center Stack
If the AP1000 timeline holds, this will be the first large-scale nuclear campus explicitly designed to power AI. That’s geopolitically significant. China has 20+ reactors under construction; the U.S. has one. If HyperGrid succeeds, it could mark the start of a domestic nuclear renaissance tied directly to AI competitiveness.
Risks Few Are Talking About
Nuclear timelines. Vogtle’s decade of overruns is the cautionary tale. Hitting 2032 is ambitious.
Capital intensity. $350M is a drop in the bucket. Fermi will need to secure $40B+ for energy infra alone.
Waste disposal. There’s still no clear plan for long-term spent fuel storage. Texas’s current sites aren’t licensed for it.
Political alignment. Branding the site the “President Donald J. Trump Advanced Energy & Intelligence Campus” may unlock short-term support but adds volatility if the political winds shift.
The Bigger Picture
The Fermi model is simple but radical:
Own the land
Build the power
Layer on compute
It doesn’t wait in interconnection queues it leapfrogs the grid. It doesn’t see energy as an input it defines it as the product. And it doesn’t separate utilities from data centers it fuses them into one sovereign-grade platform.
If it works, others will follow. If it fails, it will be remembered as a moonshot too big to finance, too complex to deliver, and too politically exposed to sustain.
Either way, Amarillo is now ground zero for the most ambitious experiment in AI infrastructure.
Final Takeaway
This isn’t just Macquarie financing a data center. It’s Macquarie underwriting a new template for the AI age: vertically integrated energy + compute, backed by nuclear, gas, and renewables, bypassing the grid altogether.
For investors, operators, and policymakers, the message is clear: control over energy is now the single most decisive factor in data center strategy.
The Amarillo HyperGrid will either prove that thesis or expose its limits.