The 90-day clause is a grid problem before it is a credit problem. A campus can cancel on a quarter's notice, but the substation and the interconnection sized for it are planned years ahead, and the load forecast behind them does not come down when the contract does. Lenders can mark the paper down; a transmission plan has no equivalent move.